Loading

Digging Deck Footings

Hand digging your footings.

Take your time and invest in a post hole digger, which will work better than a shovel to scoop out dirt. You will need to dig and remove soil until you reach the necessary size and depth specified on your approved plans. If you run into large rocks, this can become a very strenuous process. Using a 6' steel pry bar will help. When the holes are finished, you will want to clean them out by removing any loose dirt and tamping down the base and sides so that they are solid.

You can use a shovel and a post hole digger to excavate your footings by hand. The size of your footing will be determined by the amount of weight or load the footing will need to support and the type of soil in your yard. You will need to dig the footings to a depth below the frost line. For example, the footing depth in Atlanta is 24" deep, NJ is 36" and Minneapolis is 42".

To be safe, always call your utility providers before you dig. Have your gas, electric, water and other utilities marked before excavating. This service is free and usually requires about two days notice. Cable TV lines and sprinkler lines will have to be marked separately.

You may want to create a bell at the base; you can do this by expanding the bottom to the required size. Once the holes are ready, you will want to protect them from collapse until after you have had your footing inspected and can fill them in with concrete. Depending on how you plan to finish your footings, you may need to haul away the excess dirt. Plan for this or you may end up killing a great deal of your grass.

Mechanized Excavation

Most contractors use front-end loaders equipped with a hydraulic auger to dig footings. You can also rent a one or two person gas powered auger to save you considerable time and effort. With these machines, you can even dig through ice, snow and frozen soil during the winter. You will need to have yard access to drive the machine into position. Fences and certain kinds of landscaping may make this impossible. If you are going to use a machine that you are not familiar with, make sure to read the operating instructions and take proper safety precautions to prevent an accident. Be aware that driving and excavating through grass can cause yard damage. To reduce this damage, you may want to have a couple of helpers lay plywood under the vehicle's tires or use a track unit. Try to avoid driving on extremely wet yards and/or up steep hills. Even after using a mechanical auger you will still need to use a post hole digger or shovel to finish the job by cleaning out the holes and tamping down the bottom and sides. A solid base of soil will prevent the footings from sinking.

Many professional deck builders use Bobcat equipment with hydraulic augers to dig deck footings. This can really speed up the process. However, some locations, such as fenced in yards and steep slopes, can't be accessed with such large machinery. In these cases, you will need to hand dig your deck footings.

Digging Deck Footings
PinterestSave
Digging Deck Footings

Deck footings need to be dug below the frost line. Make sure the bottoms and sides of the holes are compact and solid before pouring your concrete. You can dig the footings 6" deeper than the frost line. Use a 4x4 post to compact the soil at the bottom of the hole and then add 6" of gravel for better drainage under the footing. If you are cutting the cardboard sonotubes in half with a handsaw, we recommend installing the uncut end on the top. The forms can be left in the hole after you pour the concrete.


Popular Footings Articles
Concrete

Cutting a Concrete Pad

Learn how to use a concrete saw to cut a hole in a patio slab to install a deck footing.

Footing Installation

Deck Footing Depth

Find out how deep you need to dig your footings in your area. Look at our U.S. map of extreme frost penetration.

Footing Installation

Layout Deck Foundations

Learn how to lay out your deck footings accurately using triangulation with our step-by-step instructions.

Next Step: Framing Articles
Deck Support Columns

How to Decorate Deck Support Columns

Browse some examples of decorative deck support posts for tall decks.

Deck Framing

How to Sister Deck Joists

Learn about how to sister deck joists over a beam for framing a large deck or adding onto an existing deck.

Deck Framing

How To Build a Hexagon Deck

Learn some tips on how to build a six-sided hexagon-shaped deck.

Get more helpful resources delivered right to your inbox

Explore Articles by Topic

Popular Footings Articles
Footing Installation

How many footings do I need?

Learn how to determine the number of footings and support posts you need for your deck when designing your deck frame.

Footing Types

Buried Post

Learn how to install a concrete deck footing with a buried treated support post as an alternative to a solid pier foundation.

Footing Installation

Do I need to use rebar?

Our inspector discusses using steel rebar for deck footings.

Next Step: Framing Articles
Deck Framing

Why is Joist Protection so Important for Your Deck?

If you’ve ever seen a piece of wood left out in the weather for any period of time, you know what happens: decay. Whether through wet rot, insect damage, or mildew, the fibers begin to break down.

Deck Support Columns

How to Use Steel Metal Deck Support Posts and Columns

Steel deck posts with base plates can be used as an alternative to wood posts for supporting your deck.

Deck Support Beams

How to Splice a Deck Beam Over a Support Post

Follow our step by step tutorial for splicing a deck beam over a support post. Never split a beam in the center of a span.

Get more helpful resources delivered right to your inbox

Explore Articles by Topic